Phase 1 house renovation completed



Phase 1 house renovation (a.k.a. student house setup) finally completed with the following items:

a. 23ft 2*2 concrete kitchen top
b. Work area covered-up with washing machine outlet
c. Power socket looping & lights add-on for plaster ceiling
d. Powder coated grille
e. Alarm
f. Plaster ceiling (L-box with hidden lights for living & dining, flat for kitchen)
g. Lights & fans
h. Curtain
i. Painting Interior & Exterior
j. Padlocks
k. Sharp fridge
l. Rubine hood (RCH-BOXLINE-90SS) & hob (RGH-OLIVE2B-90BL) installation
m. Kitchen tools, gas connector & gas

We have spent all our savings for these years. We really broke now. Click original house & phase 1 to view the before & after renovation.

We must work harder to save money for wedding & phase 2 (kitchen cabinet, wardrobe, bedroom set, furniture, water filter, water heater)

Home sweet home

After 5 months waiting for defect rectification & minor renovation, we have finally move in to our dream house today (8th month 8th day in Chinese lunar calendar which is also same with our ROM 080808) :D. It started with simple move-in ritual. After the ritual, the lorry mover came to our apartment to transport our stuff to new house. I did not realize we have so many boxes to move. It is unpacking time now. :D Tonight has to attend wedding dinner also. :D
Finally we have our home sweet home.

Bali, we're coming

AirAsia promotion is back. This time, we are surveying for ticket for our wedding honeymoon. After discussion with wife, we decided to visit Bali. After a few tries, we found Bali ticket which cost us RM88/person for 2 ways ticket (ticket only). We will spend our 5D4N honeymoon in Bali. Hopefully it will be a memorable days for us. Bali, we're coming.

Is it me?

The Roaster

Count down to big day

1 year from now, we will be going through our biggest day in life although we have registered 8th Aug 2008. Let the clock tick… 365, 364, 363 & … I love you.

First House

Project Proposal

14th Jul 2007: Clean up

29th Jul 2007: Foundation start

8th Sep 2007: Foundation part 2

26th Oct 2007: Foundation part 3

19th Apr 2008: House frame up

1st May 2008: Roof was ready

9th May 2008: Windows frames were up

17th May 2008: First plastering ready

31st May 2008: First layer paint applied

15th Jun 2008: External paint applied

22nd Jun 2008: Car porch roof in the making

28th Jun 2008: Car porch roof ready

12th Jul 2008: Driveway ready

13th Aug 2008: Walkway ready

9th Sep 2008: External touch up

12th Oct 2008: External touch up part 2

15th Dec 2008: External touch up part 3

15th Jan 2009: Dream house ready

26th Mar 2009: Clean up, Ready for vacant procession (key collection)

30th Apr 2009: Key Collection


After about 20 months wait, we finally got the first key to our dream house. We will be busy with defect check & minor renovation then.