Project Proposal
14th Jul 2007: Clean up
29th Jul 2007: Foundation start
8th Sep 2007: Foundation part 2
26th Oct 2007: Foundation part 3
19th Apr 2008: House frame up
1st May 2008: Roof was ready
9th May 2008: Windows frames were up
17th May 2008: First plastering ready
31st May 2008: First layer paint applied
15th Jun 2008: External paint applied
22nd Jun 2008: Car porch roof in the making
28th Jun 2008: Car porch roof ready
12th Jul 2008: Driveway ready
13th Aug 2008: Walkway ready
9th Sep 2008: External touch up
12th Oct 2008: External touch up part 2
15th Dec 2008: External touch up part 3
15th Jan 2009: Dream house ready
26th Mar 2009: Clean up, Ready for vacant procession (key collection)
30th Apr 2009: Key Collection
After about 20 months wait, we finally got the first key to our dream house. We will be busy with defect check & minor renovation then.